Location: Eastern US
Property: Chemical distribution facility
Objective: Delineate off-site solvent migration
Figure 2. 1,1,1-TCA distribution in soil gas (μg), along with 1,1,1-TCA in groundwater (μg/l).
A chemical distribution facility under RCRA Facility Investigation (RFI) noted that chlorinated solvent contamination was migrating to an adjacent site. After considering several site assessment alternatives, the site owner selected the GORE® Survey as the most cost-effective and efficient method to achieve an accurate delineation of the off-site solvent migration.
Table 1 summarizes the projected effort and costs of each assessment approach considered (1995 costs). Fig. 1 illustrates the distribution of 1,1-dichloroethane in the soil gas. The soil gas data for 1,1,1-TCA are presented in Figure 2, and reveals a slightly different subsurface distribution, which would not be captured if relying on single compound reporting. Corresponding groundwater data are also posted on the maps, and show excellent agreement with the GORE® Survey results.
Based on the successful delineation achieved by the GORE® Survey, and supported by pre-existing groundwater quality data, the site owner was able to install one additional nested well set, instead of several. The savings resulting from fewer well installations, and associated long-term O & M costs, were likely significant. From an assessment standpoint, the savings realized by using a GORE® Survey, compared to alternative site assessment approaches, was estimated upwards to $55,000 (Table 1).
| Phase | Task Item | Cluster Wells | Hydropunch, single wells | GORE® Survey | |||
|---|---|---|---|---|---|---|---|
| Qty | $ | Qty | $ | Qty | $ | ||
| I | Soil Gas Labor | - | - | - | - | 1 | $3,000 |
| Soil Gas Survey | - | - | - | - | 51 | $11,900 | |
| Single Wells | - | - | 4 | $12,000 | - | - | |
| Cluster Wells | 5 | $50,000 | - | - | - | - | |
| Hydropunch Points | - | - | - | $6,400 | - | - | |
| II | Single Wells | - | - | 2 | $6,000 | - | - |
| Cluster Wells | 2 | $20,000 | - | - | - | - | |
| Hydropunch Wells | - | - | 4 | $3,200 | - | - | |
| III | Cluster Wells | 1 | $10,000 | 1 | $10,000 | 1 | $10,000 |
| Project Total $$ | $80,000 | $37,600 | $24,900 | ||||
| Savings using GORE® Surveys | $55,100 | $12,700 | |||||